Using Maximo Oil and Gas to manage permits to work

Using Maximo for Oil and Gas, v7.5.1 to manage work processes with permits to work

The following was originally posted in the IBM Developer Works blog by Liliane Himmel 

To manage the safety of personnel and the workplace, you can define permits to work. Using corresponding work order records, you can associate tasks with permits to work. You can also associate authorized personnel with permit or certificate types to ensure that personnel have the necessary credentials to carry out those tasks. You can specify who is authorized to review and approve the permits to work. You can define the isolations and hazards that are associated with specific assets, and the actions to be taken in emergency situations. You can also create related record relationships between tickets, permits to work, and work orders.

In the Drilling and Completion application, you can review the permits to work that are related to work orders to ensure that all permits are included. Permits to work provide a system of control to ensure the safety of the plant. You can use permits to work to manage the work activities and to ensure that steps are taken to prevent accidents.

Creating permits to work

A permit to work defines the hazards and isolations that are associated with work activities. When you create permits to work, you provide the details with which the permit is associated. You ensure that permits to work are ready to be issued. Optionally, you can hold toolbox talks to communicate the safety aspects of the work activities.

A permit to work defines the hazards and isolations that are associated with work activities. When you create permits to work, you provide the details with which the permit is associated. You ensure that permits to work are ready to be issued. Optionally, you can hold toolbox talks to communicate the safety aspects of the work activities.

About this task
When you create a permit to work, you must evaluate the hazards that are involved in completing the work that is associated with that permit. You can also define the conditions for work.

In addition to creating permits to work from the Permit to Work application, you can create permits to work from the Work Order Tracking application and from the Drilling and Completion application.

Assets or locations are isolated to allow work to be carried out without hazards for personnel. Procedures are followed to contain an asset or a location before an authorized person can work on it. For example, you can specify that an asset is isolated from a potentially hazardous source of energy. When the work is complete, the steps that were taken to isolate that asset are removed so that the asset can be returned to production.

Procedure

  1. In the Permit and Certificate Types application, define a permit or certificate type to associate with this permit to work. Use the rich text editor of the Long Description field to assign a color and a font size to the text. You can assign a different color to highlight the type of permit or certificate. The highlighted text displays in the Permit Header field of the Permit to Work application.
  2. In the People application, authorize qualified, active personnel to conduct gas tests and to record emissions.
  3. In the Risk Assessment application, identify the hazards that are associated with work operations and assess their risks. Hazard records must belong to the same organization as the permit to work.
  4. In the Permit to Work application, click New Permit to Work on the toolbar.
  5. On the Permit to Work tab, specify the beginning and end dates and times, the permit level, and the site for the permit to work.
  6. Specify the asset and location details that are associated with the permit to work. If a permit to work is associated with a work order, the asset and location fields are populated from the work order.
  7. Specify the task details. If the certificate type is an isolation certificate, specify the type of isolation specialization that is required, and the reason for the isolation.
  8. On the Hazards and Isolations tab, specify the risk assessment, the gas testing details, the conditions for work, the isolations, and the hazardous materials.
  9. Save the record.

Ensuring that permits to work are ready to be issued

Verifying the conditions that are associated with permits to work

A toolbox talk is a safety presentation that is given to inform employees about safety procedures. You can also use toolbox talks to verify the conditions that are associated with the work activities. You record the attendees.

Before you begin

The permit to work must be reviewed, approved, issued, and in Active status before the toolbox talk is conducted.

The operating procedures that you add to the toolbox talk must also be in Active status. Operating procedures can be added or removed only when the permit to work is in Draft status.

About this task

You can specify the same identifier for multiple operating procedures, but the combination of organization, site, and procedure number must be unique.

Standard actions can be added when the permit to work is in Request or in Draft status. Review the checklist of standard actions during the toolbox talk. Standard actions cannot be added or removed when the permit to work is in Active status.

Items to be reviewed can include additional work hazards and control measures, or stop the job entries.

Procedure

  1. In the People application, add members of the team and their authorizations and certificates.
  2. In the Operating Procedures application, create the operating procedures to be discussed during the toolbox talk.
  3. On the Toolbox Talk tab of the Permit to Work application, specify the permit to work that requires a toolbox talk.
  4. On the Toolbox Talk tabs, specify the operating procedures, the actions or action groups, and the items to be reviewed.
  5. On the Work Party Declaration tab, specify the members of the team who attended the toolbox talk.
  6. In the Toolbox Talk Completion table, specify whether a toolbox talk was held and the person who held the toolbox talk. You also specify the date and time when the toolbox talk was held.
  7. Save the record.

Completing permits to work

Effective communication throughout the permit to work process is crucial to ensuring that risks are managed. After work is complete or if work is left to be done by another team, the details of returning the permit to work must be documented.

Canceling permits to work

When all of the work activities are complete, and the plant is returned to a safe condition, you can cancel or suspend active permits to work.

About this task

You can review and audit the permit to work before or after you close the record. Audit and survey records that are associated with permits to work must belong to the same site and organization. Before a permit to work can be closed, all isolations that are in place must be removed.

Procedure

  1. In the Permit to Work application, select the permit to work that you want to cancel.
  2. On the Cancelation Details table of the Handback and Cancellation tab, specify the cancellation details.
  3. Specify whether a lessons learned meeting was held or whether there are lessons learned that are associated with this permit to work.
  4. Specify whether this permit to work must go through an audit process. If this permit to work is linked to an audit and survey record, specify the record identifier.
  5. Specify whether the work site was cleared.
  6. Save the record.

Help! Your Maximo Questions Answered

Are you stuck on a particular Maximo question? You can either post up at the MaximoUsers.org/forum for specific questions. But, if you are looking for more general information, IBM has a wealth of information, such as manuals and training videos.  The IBM Education Assistant, or IAE, provides training videos, educational demonstrations, tutorials and other information that is targeted toward the IT professional.

The IEA has just released several new videos:

Other topic of interest:

Maximo V7.1

Maximo v7.1.1

Maximo 7.5

Information originally posted to http://www-01.ibm.com/support/docview.wss?uid=swg21373538

No OOB Maximo components

This is part of a series on Integration Framework. To read from the beginning, visit
the post IBM Maximo Asset Management Help: Integration Framework

Integrating Maximo data when there are no ‘out of the box’ integration components

Maximo provides a number of integration components (object structures, channels & services) for a wide variety of business object data, such as Work Orders, Purchase Orders and Assets.  However Maximo has over 1000 objects so there will be cases where the data you want to integrate with does not have the corresponding integration components pre-built.  In this case you need to leverage the applications provided in Maximo to create the necessary components.

Note: the description below covers the configuration steps in some of the I-F applications.  This content does not cover every possible configuration that can be done, just those relevant to the example being discussed.
Continue reading

Customize with Rules and Controls

This is part of a series on Integration Framework. To read from the beginning, visit
the post IBM Maximo Asset Management Help: Integration Framework

How to customize your integrtion message processing

If you need to customize your integration message processing but don’t want to implement Java code, one option is to use Integration Controls and Processing Rules to provide customizations that will let you filter messages and set values to fields in your integration message.

To provide customizations, you can define integration controls and then leverage those controls in Processing Rules on your Publish Channels and/or Enterprise Services. Doing this, provides a configurable approach to customizing that will allow you to easily alter your integration processing as your integration requirements change.  First, you need to create integration controls and then build processing rules that exploit those controls. Continue reading